Project Highlights & Challenges
The complete scope of 6600MT of work was successfully completed in just 11 months, demonstrating exceptional efficiency and project management. Approximately 600MT (Gridline 1 to 8) of the structure was pre-assembled outside the building and then moved into position using heavy cranes. Notably, the erection timeline for the furnace area was reduced from 30 days to an impressive 20 days, showcasing our ability to meet tight deadlines while maintaining the highest standards of safety and quality.
Project Outcome
The Vishakha Glass Pvt Ltd project highlights our commitment to delivering large-scale projects on time and within budget. We gained strong confidence in executing the project through a systematic and organized approach, ensuring every aspect was carefully planned and efficiently executed.